Specifies the dependency relationship between two rows in a Gantt chart.
Namespace: Microsoft.SharePoint.JSGrid
Assembly: Microsoft.SharePoint (in Microsoft.SharePoint.dll)
Syntax
'Declaration
Public Enumeration LinkType
'Usage
Dim instance As LinkType
public enum LinkType
Members
Member name | Description | |
---|---|---|
FinishFinish | A particular row’s finish date must be the same as this row’s finish date. | |
FinishStart | A particular row's start date must follow this row's finish date. | |
StartFinish | A particular row's finish date must come before this row's start date. | |
StartStart | Two rows must start at the same time. |