Contains constants that specify the action to take with the specified tasks.
Name | Value | Description |
---|---|---|
pj0or100Percent | 0 | Sets only the Actual Start and Actual Finish dates. |
pj0to100Percent | 1 | Sets the percent complete to reflect the update date. |
pjReschedule | 2 | Schedules the remainder of the work to start on the update date. |