Defines the predecessor task on which this task depends for its start or finish date.
<PredecessorLink>
ComplexTypeValue
</PredecessorLink>
Parent Elements
Child Elements
Element |
Required/Optional |
Description |
---|---|---|
Optional |
Unique ID number for the predecessor task. |
|
Optional |
Type of predecessor task link (FF, FS, SF, SS). |
|
Optional |
Indicates whether the task predecessor is part of another project. |
|
Optional |
External predecessor project. |
|
Optional |
Amount of lag time (in tenths of a minute) from the predecessor task. |
|
Optional |
Indicates the time format (hours, days, and so on) for the amount of lag specified in LinkLag. |
Occurrences
Minimum: 0 Maximum: Unbounded |